Japanese consortium deal sets initial revenue terms for Dhaka’s third terminal
Bangladesh would receive a share during a six-month period after an eight-month no-share phase; Biman could handle up to half of international ground services.

Bangladesh is due to receive a 13.5% share of the third terminal’s revenue for six months under a proposed operating agreement with a Japanese consortium. The terms also allow Biman Bangladesh Airlines to take on as much as half of the terminal’s international ground services.
The Cabinet Committee on Economic Affairs gave the proposal preliminary approval on Monday. Under its schedule, the government would receive no revenue share for the first eight months after handover. A six-month period would follow, during which the government would receive 13.5% of terminal revenue, according to the proposal summary.
The consortium would take responsibility for operating and maintaining the terminal for 15 years once full operations start, 14 months after handover. The proposed terms also set the government’s share at $2.10 per passenger, equal to 20% of passenger revenue, and 27% of cargo revenue, or $11.50 per tonne. The operator would pay an $8.1 million concession fee upfront, approximately Tk100 crore.
What passengers and Biman can expect
The proposed embarkation fee for passengers departing from the new terminal is $12.50, or about Tk1,560. The existing charge at Terminals 1 and 2 is Tk500. Under the agreement, Biman could handle up to half of international ground services, with another handler to be appointed during the initial operating phase for the remainder.
After Monday’s meeting, Civil Aviation and Tourism Minister M Rashiduzzaman Millat said the government aims to sign the agreement by 30 November. The terminal is scheduled to begin partial operations on 16 December, initially serving four flights, including an inaugural Biman flight. Millat said the consortium could not reach 25% capacity at once, so activity would increase in stages.
Who will operate the terminal
The Japan Sub-Working Group consortium consists of Japan Airport Terminal Co Ltd, Sumitomo Corporation, Nippon Koei and Narita International Airport Corporation. The Tk22,213 crore terminal project has been under way since 2016 and is scheduled for completion in 2027.
The agreement contains a stabilisation provision aimed at keeping later changes to domestic law from altering its terms, supported by a comfort letter from the civil aviation ministry. Full operations are expected 14 months after the December launch; no alternative timetable has been announced by the government.